Calculating over/under billing

Written by Bradley LaFave

Over/under billing compares the revenue you’ve earned with the amount you’ve billed. Siteline estimates earned revenue using your project’s costs to date, current cost budget, and contract value.


How the calculation works

  1. Completion rate = Cost to date ÷ Cost budget

  2. Earned revenue = Completion rate × Contract value

  3. Over/under billing = Earned revenue − Total billed

A positive result means you’re underbilled: you’ve earned more than you’ve billed. A negative result means you’re overbilled: you’ve billed more than you’ve earned. A result of zero means billing matches earned revenue.


View over/under billing

Open a pay app, go to the Invoice tab, and select OVER/UNDER.

empty.over.under.full.png


Import cost data from your ERP

With a supported ERP connection, Siteline can pull project cost data from:

  • Acumatica

  • Foundation

  • Sage 100 Contractor

  • Sage 300 CRE

  • Sage Intacct

  • Viewpoint Spectrum

  • Viewpoint Vista

Review your cost information before using the calculation.

updated.from.sage.png

Enter cost data manually

If you don’t have a supported integration or don’t track project costs in your ERP, enter the cost information manually. You can also add additional committed costs.

manual.cost.update.png

You can clear the cost information at any time, then import it again from your ERP or enter updated values manually.